Isn't there a deadline for the Maloofs to file for relocation?
Also, say an arena does get approved. How long would it take before it gets completely built?
On average, arenas take around 26 months to build. They break ground in the summer and are usually ready in October, 2 years later.
Best case scenario for the Kings is that ICON/Taylor doesn't hit any roadblocks and they break ground in July of 2012 and have it ready to roll in November of 2014 but that's a long shot. Taylor has to come back with a solid funding plan and since that's so tough to come by, my guess is that he'll use the full 90 days. That puts us in May of this year. Then you have to get it ok'd from the city and all the politicos plus line up contractors, bulldoze anything that's in the way and finish up the infrastructure. All that has to happen in the next 18 months for an arena to be ready by November of 2014. Long shot at best although November of 2015 should be pretty definite.